Better late than never, but never late is better: Risk assessment of nuclear power construction projects
Portugal-Pereira, J.1,2; Ferreira, P.3; Cunha, J.3; Szklo, A.1; Schaeffer, R.1; Araujo, M.3
2018-09-01
发表期刊ENERGY POLICY
ISSN0301-4215
EISSN1873-6777
出版年2018
卷号120页码:158-166
文章类型Article
语种英语
国家Brazil; England; Portugal
英文摘要

This work seeks to evaluate overnight construction costs (OCC) and lead-time escalation of nuclear power construction projects from 1955 to 2016. To this end, a comprehensive database of commercial Light Water Reactors (LWR) was developed and a statistical analysis was conducted. Findings reveal a significant delay in lead-time, especially for the last generation reactors constructed from 2010s, with 3/4 of the sample showing significant construction delays. This results in an escalation of capital costs rather than in a decline. Average OCC of newer reactors is 60% higher than the ones implemented in the earlier stages of the nuclear era. This suggests a discontinuity of the learning curve for both OCC and lead-time, which threats the market and financial sustainability of current and future nuclear energy projects. Although this is a general trend, this discontinuity is country specific and, thus, induced by national policies and regulatory frameworks. Therefore, the role of nuclear technology as an alternative to cope with the need for a decarbonisation of the power sector must be better evaluated, taking into account the real cost impacts of nuclear technology implementation.


英文关键词Nuclear energy Overnight construction costs Financial costs Risk assessment
领域气候变化
收录类别SCI-E ; SSCI
WOS记录号WOS:000440123300015
WOS关键词RENEWABLE ENERGY SYSTEM ; POST-FUKUSHIMA ; COST OVERRUNS ; ELECTRICITY INFRASTRUCTURE ; PUBLIC ACCEPTANCE ; JAPAN ; REACTORS ; PLANTS ; CHINA ; MEGAPROJECTS
WOS类目Economics ; Energy & Fuels ; Environmental Sciences ; Environmental Studies
WOS研究方向Business & Economics ; Energy & Fuels ; Environmental Sciences & Ecology
引用统计
被引频次:28[WOS]   [WOS记录]     [WOS相关记录]
文献类型期刊论文
条目标识符http://119.78.100.173/C666/handle/2XK7JSWQ/19180
专题气候变化
作者单位1.Univ Fed Rio de Janeiro, Ctr Tecnol, Energy Planning Program, Grad Sch Engn, Bloco C,Sala 211,Cidade Univ, BR-21941972 Rio De Janeiro, RJ, Brazil;
2.Imperial Coll London, Ctr Environm Policy, Weeks Bldg 16-18 Princes Gardens, London SW7 1BA, England;
3.Univ Minho, ALGORITMI Ctr, Sch Engn, Campus Azurem, P-4800058 Guimaraes, Portugal
推荐引用方式
GB/T 7714
Portugal-Pereira, J.,Ferreira, P.,Cunha, J.,et al. Better late than never, but never late is better: Risk assessment of nuclear power construction projects[J]. ENERGY POLICY,2018,120:158-166.
APA Portugal-Pereira, J.,Ferreira, P.,Cunha, J.,Szklo, A.,Schaeffer, R.,&Araujo, M..(2018).Better late than never, but never late is better: Risk assessment of nuclear power construction projects.ENERGY POLICY,120,158-166.
MLA Portugal-Pereira, J.,et al."Better late than never, but never late is better: Risk assessment of nuclear power construction projects".ENERGY POLICY 120(2018):158-166.
条目包含的文件
条目无相关文件。
个性服务
推荐该条目
保存到收藏夹
查看访问统计
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Portugal-Pereira, J.]的文章
[Ferreira, P.]的文章
[Cunha, J.]的文章
百度学术
百度学术中相似的文章
[Portugal-Pereira, J.]的文章
[Ferreira, P.]的文章
[Cunha, J.]的文章
必应学术
必应学术中相似的文章
[Portugal-Pereira, J.]的文章
[Ferreira, P.]的文章
[Cunha, J.]的文章
相关权益政策
暂无数据
收藏/分享
所有评论 (0)
暂无评论
 

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。